Engagements

Three engagement sizes, one model.

Each size applies the same model of the software–hardware stack and its uncertainties, and the same optimiser, at a different depth: a fast risk scan of a design already on the table, a full optimisation study of what to build, or an ongoing scenario simulation as plans change. All three are simulation work on design documents and inputs you send. Fixed scope and fixed fee, agreed before work starts.

The flow

What happens in every engagement.

  1. 01You send the documents

    The design basis, drawings, equipment list and the decision you face. We do not connect to your systems.

  2. 02We model, then optimise

    The stack and its uncertainties go into one model. A large-scale optimiser returns the points that match your risk profile.

  3. 03You receive a decision memo

    Expected cost, tail risk and a recommendation, with the auditable model handed over.

What you get

Deliverables at each size.

Same model, different depth. Durations are indicative and fixed at scoping. No access to your systems at any size: design documents and inputs only.

T1Fast risk scanT2Full optimisation studyT3Ongoing scenario simulation
Question answeredIs this design safe to build?What should we build?Is the plan still optimal after the latest changes?
You get
  • Risk register with probabilities and owners
  • Scenario simulation model (auditable)
  • Ranked list of design changes
  • Jointly optimised concept design
  • E[TCO] + λ·CVaR report with frontier
  • Decision memo for the investment committee
  • Simulation report per re-run
  • Updated optimised design
  • Decision memo: what changed and why
OutcomeA go / change decision on the current design, with its tail risk stated.One concept, defended on expected cost and tail risk, ready for detailed design.Expansion, refresh and sourcing decisions re-tested by simulation each time the inputs change.
Access to your systemsNone: design documents onlyNone: design documents onlyNone: simulation on inputs you send
Indicative duration≈ 4 weeks≈ 8–12 weeksOngoing · periodic
Typical next stepA full optimisation study, or detailed designDetailed design, then ongoing scenario simulationThe next scheduled re-run

T3 is simulation only: we re-run the model on the updated documents and inputs you send.

See an illustrative decision memo →

Method

How an engagement runs.

The same five steps at every tier; the depth changes, not the discipline.

  1. 01

    Frame

    The decision, the options on the table, and the risk budget (α, ε) and acceptance criteria, agreed with you.

    OutputDecision brief

  2. 02

    Encode

    Workload, servers, racks, power chain, cooling plant and supply chain as one parameterised model, built from your design basis.

    OutputSystem model

  3. 03

    Quantify uncertainty

    Distributions for load growth, accelerator power, climate, failures, prices and lead times, fitted to your data, vendor data and published field data.

    OutputAssumption register

  4. 04

    Simulate and optimise

    Monte Carlo and reliability models; chance-constrained and two-stage stochastic programs; the risk–cost frontier and its sensitivities.

    OutputFrontier and sensitivities

  5. 05

    Decide and hand over

    A recommendation with its expected cost and tail risk, and the documented model, so your team can audit and re-run every number.

    OutputDecision memo and model

The model

Five layers. One decision vector.

Density sets cooling; cooling sets the power path; the power path sets what you can buy, and when. We decide them together.

Full-stack joint optimization architecture for an AI datacenter
Full-stack joint optimization architecture for an AI datacenter
Figure AFull-stack joint optimization. Stochastic inputs ω are sampled into scenarios; decisions x at every layer are chosen together to minimise E[TCO] + λ·CVaR, subject to chance constraints. Schematic.

What you get

A result you can take to an investment committee.

Options compared on expected cost and tail risk under the same scenarios, with the probability of each failure mode stated, not implied.

Illustrative

Concept comparison, 40 MW IT hall

Synthetic numbers to show the format of a result. Not from any client or project. Risk budget: εT = 2% per year, α = 0.95.

OptionCooling · power pathE[TCO / GPU-h]
index
CVaR0.95
index
P[thermal
excursion] / yr
P(energised
by target)
Reading
ADirect-to-chip, W32 · AC, 2N1001120.8%0.71Safe, but reserve power is stranded
BDirect-to-chip, W40 · shared reserve + capping941031.9%0.78Recommended. Lowest cost and tail within ε
CTwo-phase immersion, W40 · AC, 2N971210.6%0.52Best thermal margin; fluid and supply tail

Index: option A = 100. Lower is better for cost and CVaR. Every number in a real report traces to the assumption register.

Illustrative probability of energisation by month for two procurement strategies
Figure BSchedule risk as a model output: probability of energisation by month under two procurement strategies, with P10–P50–P90 bands, from lead-time distributions. Illustrative, synthetic data.

T1≈ 4 weeks

Fast risk scan

Your planned AI hall, scored for tail risk before you build.

For

Owners, developers and operators with a design basis or a reference design they are about to commit capital to.

You provide

  • Design basis: IT load, platform, rack density, phasing
  • Single-line and heat-rejection concept
  • Site climate, utility and water constraints
  • Equipment list with quoted lead times

Typical questions

Process

  1. Ingest the design and encode it in the model
  2. Fit distributions: load, power, climate, failures, lead times
  3. Monte Carlo over the design as drawn
  4. Rank changes by risk removed per unit cost

Deliverables

  • Risk register with probabilities and owners
  • Scenario simulation model (auditable)
  • Ranked list of design changes

Reported as

CVaRα[TCO] · P[thermal excursion] · P[power cap] · P[late delivery]

OutcomeA go / change decision on the current design, with its tail risk stated.

Illustrated byUC 05 · Cooling under-provisioning UC 06 · Environment and reliability

Scope an assessment

T2≈ 8–12 weeks

Full optimisation study

The software–hardware stack, jointly optimised under your risk profile.

For

Teams choosing a concept for a new hall or generation: density, cooling technology (incl. immersion), power path, W-class.

You provide

  • Target workloads and platform roadmap
  • Site, utility and water envelope
  • Candidate technologies and vendors
  • Cost basis and the agreed risk budget

Typical questions

Process

  1. Parameterise candidate topologies across all four disciplines
  2. Optimise jointly: min E[TCO] + λ·CVaRα
  3. Trace the risk–cost frontier
  4. Select, stress-test and document the concept

Deliverables

  • Jointly optimised concept design
  • E[TCO] + λ·CVaR report with frontier
  • Decision memo for the investment committee

Reported as

E[TCO] · CVaRα · chance constraints εT, εP, εW, εS

OutcomeOne concept, defended on expected cost and tail risk, ready for detailed design.

Illustrated byUC 01 · Two-phase immersion (2PIC) UC 03 · Stranded redundant power UC 07 · Life-cycle impact of cooling

Scope a study

T3Ongoing · periodic

Ongoing scenario simulation

The same model, re-run when plans, hardware or suppliers change. Simulation only.

For

Owners and operators with a phased build-out or refresh roadmap, whose plans, hardware and suppliers keep changing.

You provide

  • Updated capacity and expansion plans
  • New hardware generations and platform specs
  • Supplier quotes and lead-time changes
  • Revised assumptions and scenarios to test

Typical questions

Process

  1. Agree the re-run cadence and scenario set
  2. Update model inputs from your revised plans
  3. Re-run the simulation; re-optimise
  4. Review what changed since the last run

Deliverables

  • Simulation report per re-run
  • Updated optimised design
  • Decision memo: what changed and why

Reported as

P50 / P90 / P99 capacity per phase · Δ E[TCO] and Δ CVaRα vs last run · P[late delivery]

OutcomeExpansion, refresh and sourcing decisions re-tested by simulation each time the inputs change.

Illustrated byUC 02 · Cooling technology selection UC 04 · Power oversubscription

Discuss ongoing simulation

Decisions we price

Questions usually answered with one number. We answer with a distribution.

Each is a joint question across software, servers, power, cooling and supply. Each comes back as an expected value, a tail and a recommendation.

Q01

How far can we oversubscribe power?

Rack, row and hall draw simulated against breaker, UPS and utility limits per failure domain; the capping policy sized so critical jobs are rarely touched.

Reported asρ at P[cap on critical] ≤ ε · stranded MW

0102UC 04UC 03

Q02

Direct-to-chip liquid cooling or two-phase immersion (2PIC)?

Each option scored on sustained clocks, facility-water class, fluid and supply risk, and cost, not on peak TDP.

Reported asE[TCO / GPU-h] · CVaRα · P[thermal excursion]

0301UC 01UC 02

Q03

Will we be energised on the date in the plan?

Transformer, switchgear, generator and CDU lead times as distributions, propagated through the build schedule.

Reported asP(energised by date) · critical-path items

0402

Q04

Grid-limited site: phase the load, add storage or generate on site?

Interconnect capacity, phased energisation and on-site options traded against the compute ramp you need.

Reported asMW-months of deferred compute · E[TCO]

0304

Q05

How do we absorb synchronous training power swings?

Job-level swings simulated against UPS, BESS and utility ramp limits; power floors, staggered checkpoints and storage sized together.

Reported asdP/dt at P99 · storage kWh · throughput cost

0103

Q06

How much redundancy, and how many spares?

Availability model with failure distributions, MTTR and spare pools per failure domain: N+1, 2N, or reserve shared with workload shedding.

Reported asP[SLA breach] · spares per pod · stranded power

0201UC 03

Q07

Can we provision cooling below the coincident peak?

The joint distribution of IT load and weather, rather than their stacked maxima, sets plant capacity.

Reported asP50 / P90 / P99 heat load · capacity at ε

0203UC 05

Q08

Which facility-water temperature?

Economiser hours and chiller trim traded against junction-temperature margin and leakage at the cold plate.

Reported asHours at limit per year · Δ E[TCO]

0302UC 06

Q09

What does a GPU-hour cost at P90, not P50?

TCO under uncertainty: energy, water, failures, capping, delivery delay and refresh, in one model.

Reported asDistribution of TCO / GPU-h · CVaRα

02UC 05UC 07

Numbers 01–04 refer to the practice areas on this page. UC links go to published work on the same question.

01Optimiser

Joint software-hardware optimization of datacenters

Cray XE6 cabinets, Blue Waters supercomputer, NCSA.
Cray XE6 cabinets, Blue Waters supercomputer, NCSA. Photo: Stevek ncsa, CC BY-SA 3.0, via Wikimedia Commons; converted to greyscale.

Placement, capping, clock and checkpoint policies are simulated against UPS headroom, CDU and facility-water capacity, and thermal ride-through, then optimised with the plant. Stranded watts become capacity; training swings are shaped in the design.

Uncertain
GPU failures, job interruptions, training power swings.
We quantify
Goodput per MW, checkpoint interval, spares per pod.
  1. Co-design specification: signals (P, Tj, flow, ΔP) and levers (caps, placement, clocks, CDU setpoints), sized by simulation
  2. Oversubscription and capping policy, simulated per failure domain
  3. Training power-shaping spec: floors, staggered checkpoints, rack and site storage
  4. Thermal-headroom envelope: sustained boost vs power and reliability cost
Illustrative synchronous training power trace, raw and shaped
Figure 1.1Training power trace, raw and shaped. Illustrative.

02Model

Stochastic modeling and optimization

Blue Waters main data hall before IT installation, 2010.
Blue Waters main data hall before IT installation, 2010. Photo: Daniel Schwen, CC BY-SA 4.0, via Wikimedia Commons; converted to greyscale.

Growth, accelerator power, climate, failures, prices and delivery dates are distributions. We build Monte Carlo and reliability models and solve chance-constrained, two-stage programs over them.

Uncertain
Load, weather, failures and lead times, all at once.
We quantify
Expected cost, its tail (CVaR) and P[miss] against your risk budget.
  1. P50 / P90 / P99 envelopes for power, cooling and water over the build-out
  2. Availability model: failure distributions, MTTR, spares, SLA exposure
  3. min E[TCO] + λ·CVaRα s.t. P[excursion] ≤ ε
  4. Auditable simulation model, documented
Risk versus cost frontier for candidate AI datacenter designs, illustrative
Figure 2.1Risk–cost frontier over candidate designs. Illustrative.

03Driven by the model

State of the art software, server, electrical, mechanical concept design

4.16 kV distribution switchgear.
4.16 kV distribution switchgear. Photo: Rsparks3, CC0 1.0, via Wikimedia Commons; converted to greyscale.

Concepts for 100 to ~600 kW racks. Cold plate or two-phase immersion (2PIC), AC or 800 VDC, W-class: each option is parameterised and traded on expected cost and tail risk.

Uncertain
Cooling margin at 100 kW+ racks; reserve power left idle.
We quantify
P[thermal excursion] per year; usable reserve capacity.
  1. Concept basis across software, server, electrical and mechanical
  2. Single-line and heat-rejection concepts for rack, row and hall
  3. Technology selection with quantified trade-offs
  4. Acceptance criteria and test plans for detailed design
Power and cooling co-design one-line with stochastic inputs feeding the optimizer
Power and cooling co-design one-line with stochastic inputs feeding the optimizer
Figure 3.1Power-and-cooling co-design one-line. Tags ω mark where uncertainty enters the optimizer. Schematic.

04Feeds the model

Supply chain risk integration

Substation transformer, Muurame, Finland.
Substation transformer, Muurame, Finland. Photo: Antti Leppänen, CC BY 4.0, via Wikimedia Commons; converted to greyscale.

Long-lead equipment now sets the schedule. Lead times, sourcing concentration and regulatory exposure (e.g. PFAS fluids) become distributions, so every design choice carries its delivery risk.

Uncertain
Transformer and switchgear lead times; the grid energisation date.
We quantify
P[energised by target date]; the critical-path items.
  1. Supply-risk register per BOM line
  2. Schedule-risk simulation: P(energisation by date)
  3. Design for substitution and second source
  4. Procurement inputs: early release, buffers, spec flexibility
Illustrative lead-time distributions for long-lead AI datacenter equipment
Figure 4.1Lead-time distributions as model inputs. Illustrative ranges, not market quotes.

FAQ

Common questions.

What happens on the scoping call?

We discuss the decision, the scale and the binding constraints, and agree the questions the model would answer and the inputs it needs. Afterwards you receive a scoping note with the recommended engagement and a fixed scope and fee.

What exactly is ongoing scenario simulation (T3)?

A scheduled re-run of the same model whenever your plans, hardware generations or supplier quotes change. You send updated inputs; we re-simulate, re-optimise and report what changed and why. It is simulation only: we do not connect to, operate or control any of your systems.

What do you need from us to start?

For a fast risk scan: the design basis (IT load, platform, rack density, phasing), single-line and heat-rejection concepts, site climate and utility constraints, and the equipment list with quoted lead times. Where data is missing we use published field data and record the assumption.

How is the work priced?

A fixed fee for a fixed scope, set out in the scoping note and agreed before any work starts.

Do you replace our design firm or engineer of record?

No. We work at concept and decision level and hand over acceptance criteria for detailed design. Detailed design, sign-off and construction stay with your design and delivery partners.

Can you work under NDA and with sensitive designs?

Yes. Engagements run under NDA. We need design-level documents, not access to production systems.

What do we keep at the end?

The decision memo, the assumption register and the documented simulation model, so your engineers can audit every number and re-run it.

Is this only for new builds?

No. The same model applies to retrofits such as adding liquid cooling to an air-cooled hall, to hardware refresh cycles and to phased expansions.

Who does the work?

Engineering is based in Zürich; the company is registered in Ireland. Work is run remotely, with site visits where the scope needs them.

Not sure which engagement?

Send the design basis and the decision you face. We recommend one in the scoping note.